For speedy resolutions of change in Law issues pending between
Generating Companies (Gencos) and the Distribution Companies (Discoms), a draft
rule has been notified on Change in Law & Must Run Status. The objectives
of the draft rules are righteous, and an attempt has been made to bring in
clarity and uniformity across the country. This will also help the government
in expediting revenue collection. Afterall, Government of India is the ultimate
beneficiary of most of the change in law cases; be it imposition of increase in
royalty or imposition of DMF /NMET charges on mined coal, imposition of clean
energy (coal) cess, increase in railway freight or changes in taxes like GST
& custom duty etc. These change in law items ultimately add to the cost of
power and make electricity expensive.
The change in law event has been fairly defined in the draft rule by incorporating all
relevant provisions used in any standard PPA and various orders of the courts
pronounced so far , however, there are few serious issues which may arise in
implementation of these rules if they are
notified in its current form. Further, It will be very interesting to see how
this rule on “Change in law” will be implemented itself as a change in law
event.
There appears to be no problem If the change in law is relating only
to increase in taxes and duties, because once such change in law event is notified,
the generating companies has to claims the bills from the effective date of
notification of the law and the procurer or discoms has to pays the dues. Final
adjustments are carried out in the true-up of audited accounts. If there are
disputes, the regulator decides the matter.
But the situation will be different for other change in law cases
especially those relating to environmental laws. An important issue in this
regard will be that of prospectivity vs retrospectivity. While the rules will
apply prospectively, it is not clear whether its applicability will be only on
future change in law events or all including those which have been notified prior
to the notification of rules? Further, whether it will apply only on
prospective biddings / tariff determination cases or on all cases including the
past ones? The draft rule language appears to be nuanced with the intention to apply
on all past cases of change in laws also including those notified prior to
notification of the proposed rule. This can be seen from the language of Rule
2(b) read with Rule 3(e) having provision of “come into effect automatically
after 30 days of the change is law event”.
“Rule-2(b) “Change in Law” means the occurrence of any of the following events after the date of submission of bids in case of tariff based bidding under Section 63 of the Act or after the determination of tariff by the Appropriate Commission under Section 62 of the Act.”
“Rule 3(b) The pass through will happen in an expeditious manner within a maximum of 30 days of the Change in Law event. “
“Rule 3(e) The pass through according to the formula stipulated above shall be calculated and shall come into effect automatically after 30 days of the Change in Law event. “
A summary table highlights the consequences of these rules.
Rule 3(b) & 3(e)
applicability |
On Change in laws |
On PPA’s |
Prospective |
No Problem |
No Problem |
Retrospective |
Problem |
Problem |
Presently, the cases of change in environmental laws are examined
in context of difference between the applicability of existing standards and
new standards on the plant & PPA .Further, compliance of change in
environmental laws involves additional capital investment and operating costs
which cannot be normative and must be computed on actual basis because every
plant has different operating parameters and environmental clearance
conditions; and are subjected to transparent process & prudence check. For
example-
Emission
Rules notified by MoEF & CC
Date of
COD of Thermal Plant |
Particulate
Matters (PM) in mg/Nm3 |
SO2
(mg/Nm3) |
NOx
(mg/Nm3) |
Mercury
(g/Nm3) |
Before
31.12.2003 |
100 |
600 for
< 500 MW 200 for
>500 MW |
600 |
.03 for
>500 MW |
After
1.1.2004 & before 31.12.2016 |
50 |
300 |
300 |
.03 |
On or
after 1.12017 |
30 |
100 |
100 |
.03 |
Further, the rule, being senior in hierarchy to the regulations
and the PPAs, will supercede the existing mechanisms of compliance. Though
legally, retrospectivity may not sustain, but will cause multiple litigations
& delays before ultimately it is conclusively settled by the Supreme Court.
Another interesting part is relating to the formula given in
Annexure-I for calculating the impact of change in law event. This formula is
for only non-recurring cost and RE power whereas, in practice, thermal power
plants are more affected because of their legacy issues. Also, the impact on
change in law may be on both, recurring and non-recurring cost of the plant e.g.
FGD equipment’s need more water and power which are met through increased
auxiliary consumption by burning more coal and thereby increasing its O&M
cost.
The part of the rule relating to the Must Run plants appears be
fine except that it adds “all other Renewable Energy Plants”. While there are
no issues with Solar , wind or Hydro power plants as must run, but other RE
plants like bagasse based plants, which are not intermittent and use baggage as
fuel, should not be given status of must run because unlike solar/hydro or
wind, bagasse can be stored. Therefore, there appears no ground to include them
in the must run list.
Also, the charges payable to the must run RE plants for their curtailment
on grid security reasons should be borne by ancillary services mechanism and
not the discoms, because it is the system operator (SLDC/RLDC) which decided
curtailment on grid security and not discoms. It is expected that Ministry of
Power will address these deficiencies/ issues in their final notification.
About the Author:
Raj Pratap Singh retired from IAS has worked at
senior positions at Central & State Government including PMO and World
Bank. Presently he is Chairman of UP Electricity Regulatory Commission.
Disclaimer: Views expressed in this article are
author’s opinion and does not reflect any official position
Comprehensive comments sir....
ReplyDeleteThe draft electricity rules seem to be another feather to the bouquet of accelerating RE development .....? Automatic recovery of change in law, compensation for non scheduling of RE Power and even truing up of competitively bid tariff .....what about the balance between the generator and discom...which is the essence of electricity act 2003....